CAPITAL PROJECTS COST CONTROL

 

In light of the 2017-2018 Construction Forecasts, Capital Projects Cost Control is paramount and one to take a more acute focus.

In Project Execution, Field Labor Shortages Represent The Highest Risk To Achievement Of Time & Cost Objectives Large And Complex Projects.

Major Shortages in Construction Field Labor Will Influence (Negatively) US Construction Costs.

In Execution (After Stage Gate Three), A Major Risk to Project Cost Management Resides in Labor Cost (overruns),

The Highest Risk to Achieving Project Cost Management Occurs In Execution – After Stage Gate Three/Full Funding.

Driven By A Long History of Cost and Schedule Overruns, Managerial Thinking Now Prioritizes Cost Certainty.

On Complex Capital Projects, Cost Certainty Has Become a Compelling Objective.

 

McLaughlin & McLaughlin has assisted numerous  Major Capital Projects successfully over the years by providing cost effective business solutions and recovery plans.

What makes McLaughlin & McLaughlin unique from the others is that we  not only perform project management services but dispute resolution as practitioners.

 

It is important to note that McLaughlin and McLaughlin Project and Dispute Consulting LLC [M&M] is not a law firm and is not intending to provide legal advice.  M&M is a consulting firm providing (among other services) non-legal expertise in construction claims, dispute resolution and litigation support.   For further information on M&M services, please see www.McLaughlinandMcLaughlin.com.

 

LABOR OVERRUNS

As the increase of projected Major Capital Projects for 2017-18 emerge with all its implications troubled projects are a likely result.  LABOR OVERRUNS are a typical component in troubled projects.

LABOR OVERRUNS – impact several project baselines. Cost, Schedule and Progress are at risk.

LABOR OVERRUNS – Labor Overruns are a major risk in any project with a significant labor component.

LABOR OVERRUNS – Early detection, correction and management require use of proper KPI’s.

LABOR OVERRUNS – Use of thoughtful KPI’s facilitate early/proactive corrective action.

LABOR OVERRUNS – Labor Shortages in 2017 and beyond will lead to upward pressure in labor rates.

LABOR OVERRUNS – Labor shortages in 2017 and beyond will lead a man-hour overruns (poor productivity).

McLaughlin & McLaughlin has assisted numerous troubled Major Capital Projects successfully over the years by providing cost effective business solutions and recovery plans.

 

It is important to note that McLaughlin and McLaughlin Project and Dispute Consulting LLC [M&M] is not a law firm and is not intending to provide legal advice.  M&M is a consulting firm providing (among other services) non-legal expertise in construction claims, dispute resolution and litigation support.   For further information on M&M services, please see www.McLaughlinandMcLaughlin.com.

CAPITAL PROJECTS MANAGEMENT – US Gulf Coast

Capital project construction forecasts (US Gulf Coast) concur regarding robust project activity and growth for calendar years 2017 and 2018.  These glowing forecasts are tempered with forecasts of craft labor, field supervision and project/construction management shortages.  Demand for experienced project resources is expected to exceed supply.  This is similar to Venezuela (post-nationalization), Canada (oil sands expansion) and other marketplace imperfections.  M&M has evaluated these forecasts and rationalized the supply and demand implications as well as professional managerial options and paths forward.  This is an emerging and dynamic managerial, consulting and legal business opportunity.  M&M’s recent and extensive work in the field at active job sites of large and complex projects confirms the emerging situation.  Here are a few topics, questions and/or observations:

  • Skilled, experienced and dynamic management will be required.
  • Cost and/or Schedule Certainty is clearly at risk regardless of the development and delivery system (PMI, CMAA, CII, AACE, IPA, proprietary or other systems).
  • Construction schedules will be driven or constrained by human resource shortages (field labor, engineering, project management).
  • Managerial planning and management must focus on:
    • Acquisition of adequate supervision and field labor force
    • Optimization of your field labor (and engineering labor).

 

It is important to note that McLaughlin and McLaughlin Project and Dispute Consulting LLC [M&M] is not a law firm and is not intending to provide legal advice.  M&M is a consulting firm providing (among other services) non-legal expertise in construction claims, dispute resolution and litigation support.   For further information on M&M services, please see www.McLaughlinandMcLaughlin.com.

https://twitter.com/McLaughProject

https://www.facebook.com/McLaughlin-McLaughlin-Project-and-Dispute-Consulting-LLC-134974839908446/

Labor Productivity

Project Professionals a blog by McLaughlin & McLaughlin Project and Dispute Consulting LLC   will be offering a few project tips regarding Project Management and Labor Productivity  over the next few weeks.

Labor Productivity – Productivity Factor (PF) according to #AACEI equals Actual Productivity divided by Baseline or Planned Productivity.

Labor Productivity – Performance Factor (PF), according to Schwartzkoff equals Estimated Unit Rate divided by Actual Rate.

Labor Productivity – A simple KPI is the ratio of Planned Man-Hours divided by Actual man-hours – “Earned over Burned.”

Labor Productivity – There are several KPI’s that can be used for project/construction management.

Labor Productivity – Use of labor productivity KPI facilitates proactive project management.

Labor Productivity – As a leading Indicator, Labor Productivity represents an excellent management tool.

 

It is important to note that McLaughlin and McLaughlin Project and Dispute Consulting LLC [M&M] is not a law firm and is not intending to provide legal advice.  M&M is a consulting firm providing (among other services) non-legal expertise in construction claims, dispute resolution and litigation support.   For further information on M&M services, please see www.McLaughlinandMcLaughlin.com.

https://twitter.com/McLaughProject

https://www.facebook.com/McLaughlin-McLaughlin-Project-and-Dispute-Consulting-LLC-134974839908446/

CONSTRUCTION CLAIMS and DISPUTES – (Part 9) Why Scope of Work?

Why Scope of Work?

This McLaughlin and McLaughlin (M&M) post is the ninth in a Subject Series  Construction Claims and Disputes.

Scope of Work is (or should be) the basis for most claims and disputes.  As we previously discussed, claims and disputes regarding scope of work are a widespread problem and represent the most common issue.  Perhaps 75 to 90% of all engineering and construction claims and disputes involve contract scope of work.  But the issue goes further.  Scope of work influences and is a foundation for delay, acceleration, disruption, payment and many other types of disputes.  Consequently, virtually all claims (should) start with scope of work.

Scope of work is a huge factor in capital investments.  In the engineering and construction market, investments total in the hundreds of billions of dollars (USD).  These investments are increasing, particularly in areas such as the US Gulf Coast.  Typical budgets for changed work are targeted for 10% which makes this market of tens of billions of dollars (USD).  However, this is merely the budget, not the reality.

Most of these investments involve contracting for goods and services.  Each of these transactions must consider scope of work (services, facilities, supply) as primary to the transaction.  Consequently, each transaction has risk of claims and disputes regarding the related scope of work.  Stakeholders include: owners, prime contractors, subcontractors, engineers, architects, lawyers, consultants, investors, lenders, sureties, governments and others.

Recognition, entitlement, pricing and proving (if necessary) claims for additional compensation related to scope of work is a huge challenge with large amounts of money at risk.  Largely, this is not legal work.  However, it requires expertise.  If the project team lacks this expertise, a subject matter expert (SME) is needed.  The SME must possess the expertise in recognition, entitlement, pricing, evidence and related impacts to the project’s performance (time, cost, and other considerations).

[Read more…]

CONSTRUCTION CLAIMS and DISPUTES – (Part 8)

Scope of Work Impacts

This McLaughlin and McLaughlin (M&M) Project Professionals post is the eighth in a Subject Series Construction Claims and Disputes.

Recent posts (Parts 6, 7) address scope of work within the overall subject of Construction Claims and Disputes.  Claims and disputes regarding scope of work are a widespread problem and represent the most common issue.  Perhaps 75 to 90% of all engineering and construction claims and disputes involve contract scope of work.  However, this is not confined to engineering and construction.

Direct compensation for a scope of work change may merely be the proverbial “tip of the iceberg.”  What about the rest of the story?  Is the contractor missing many other costs or schedule impacts?  Often, this is the case.  This issue may be broader that an added piece of equipment, redesign to avoid a conflict or similar events.

Scope of work disputes are building blocks to other claim elements in the dispute.

  • Delay – Changes can add work to the project critical path.  If so, this would cause the forecasted project completion date to be extended (potentially later than planned).
  • Progress – Changed work adds to the overall project work content, thereby changing the progress measurement and reporting (Earned Value).
  • Disruption / Productivity – Changed work impacts field labor productivity, a major risk to contractors.
  • Overheads / Indirects – Changed work may add requirements for additional construction support, supervision, insurance and other indirects.
  • Terms and Conditions – The cost of bonding, insurance, warranties, guarantees, and many others can be impacted by changed work.
  • Profit / Fee – proper compensation in this area can be challenging.

The majority of the discussion will address entitlement to recovery (rather than pricing or quantum).  For pricing (or quantum), please see McLaughlin & McLaughlins Project Professionals Construction Claims and Disputes Part 4  and Part 5[Read more…]

PROJECT PROFESSIONALS POSTING RESUMPTION

McLaughlin and McLaughlin [M&M] is pleased to announce that they will resume postings at their blog, Project Professionals.  Since mid-2013, M&M has been heavily involved with several large assignments [Construction claims regarding several power plant projects].  Now that workload permits, new blog postings will be offered.

M&M wishes to remind followers (new and ongoing) that there are many offerings at the Project Professional site.  They are organized by what we call Subject Series.

These Subject Series  are:

M&M will resume with additional posts in the Subject Series Construction Claims and Disputes.  This Subject Series focuses on methodologies, process, reference resources, techniques and other practical advice regarding the preparation, evaluating and managing construction claims and disputes.

We hope that you will find these existing and new posts informative and relevant.

We wish you the best of luck in this New Year.

 

Please note that McLaughlin and McLaughlin [M&M] is not a law firm and is not intending to provide legal advice.  M&M is a consulting firm providing (among other services) non-legal expertise in dispute resolution and litigation support.  The Resource Center is for the convenience of blog visitors and M&M does not offer this for commercial purposes.  For further information on M&M services, please see www.McLaughlinandMcLaughlin.com.

A View from the Field Project Execution / Contracting Strategies Large and Complex Industrial Projects

This article from the Division 1 of the ABA Forum on the Construction Industry Newsletter “The Dispute Resolver” represents George T. McLaughlin’s “View from the Field” formed throughout the course of his 30+ year career in the industrial marketplace.[1]   His article is broken into four parts.  Part 1, below, describes the evolution of the delivery systems in large and complex industrial projects[2]. The remaining sections, which we will publish in our next three newsletters, will discuss the legal implications (Part 2), impact on claims, disputes, and resolutions (Part 3), and prevention and corrective processes (Part 4).

Part 1 of 4 – Framing the Issue 

When the earth’s tectonic plates shift, unless there is a resulting earthquake, it goes unnoticed.  The movement is not perceptible.  Nevertheless, major changes are occurring.  In large and complex projects, with three to five (or longer) year schedules, industry shifts may not be perceptible.  Nevertheless, major changes and related impacts may be in progress.  Trends and changes in project execution and contracting strategies are similar.  These trends, however gradual and unnoticed on a daily or monthly basis, cause major impacts on existing and future projects.  While industry experts cite or drive these changes, the impact on the field may be delayed or go unrecognized by many, if not all stakeholders.  The business motivations driving the trends discussed below are varied and complex.  Perhaps, the central theme is risk tolerance or management.  The large worldwide prime contractors (typically Engineer Procure Construct) migrated toward limiting major risks by limiting scope of work, insisting on reimbursable cost (as opposed to fixed price) commercial  terms, or both.  Owners chose to limit or compartmentalize risks by breaking scope of work into smaller packages and seeking fixed price on these smaller packages.  Construction Contractors retained a willingness to work on fixed price commercial terms; but, increased their tendency toward claims and disputes processes in order to manage their risks.  Collectively, we see a myriad of fixed price scope of work packages being pieced together to form a complete project.  Formerly, this mosaic of work scopes was under one Prime Contract. [Read more…]

PROJECT PLANNING – (Part 5)

A Key Planning Resource

Industrial Megaprojects by Edward W. Merrow (Merrow, 2011)

This post is the fifth in a series of discussions regarding challenges in project planning and management situations.  In this series, we focus heavily on program / project planning and management.  This post addresses a major resource that can be highly useful in the planning and initial management of large and complex projects.

This resource is Industrial Megaprojects by Edward W. Merrow.   The subtitle is Concepts, Strategies, and Practices for Success.  This subtitle is particularly appropriate and compelling.

While the title is focused on “megaprojects,” the advice and guidance has value and merit in considering the planning and management of large and complex projects.  Smaller projects may be better guided by previous Project Professionals discussions.  Some of the key discussions are summarized in the previous post, PROJECT PLANNING (Part 4) Summary of Posts.

As presented on the dust cover of this fine book, “Mr. Merrow is the founder and CEO of Independent Project Analysis, Inc. (IPA), the world’s leading consulting firm evaluating billion-dollar megaprojects of national and international oil, chemical, pharmaceutical, and major mineral companies, and benchmarking their cost, schedules, safety, startup, and operational performance.”

While this lofty description can be both impressive and intimidating, the book has a wealth of information regarding project planning and initial execution. [Read more…]

PROJECT PLANNING (Part 4)

Summary of Posts

This summary update provides readers with an overview of prior posts regarding Project Planning and provides a baseline for future posts that will follow on a timely basis.

There are two applicable Subject Series.  One Subject Series, PROJECT MANAGEMENT CHALLENGES  was posted during June through September 2011.  Since that time, blog readership has increased very significantly.

The other Subject Series, PROJECT PLANNING  was started in late 2012.  This Subject Series is ongoing and new posts will occur in the upcoming weeks and months.  Readers are encouraged to subscribe to automatic update notification.

This summary is very brief and simply serves as an index for readers to follow.  Of course, detailed descriptions are contained in the individual posts.

Ideally these Subject Series  provide a starting point to investigate best practice on many planning and execution features of project management. [Read more…]