MANAGING RISK OF DELAY – Managing Contractor Schedules (Part 13)

This McLaughlin & McLaughlin post is the thirteenth (13th) in a series  of discussions regarding various aspects of time management as it relates to the risk of delay.  This post addresses managerial considerations for dealing with schedules prepared by contractors and submitted to owners or their agents (construction managers, managing contractors, advisors, etc.).

Recently, Mr. Chris Carson authored an excellent article titledDealing with Contractors Schedules That Cannot be Approved.  This fine article was published in COST Engineering(September/October 2013).

This article contains excellent advice for project teams regarding schedule management.

Mr. Carson’s article is, in reality two articles in one.  While Mr. Carson’s article presents a methodology for problematic situations (which he calls DSAB), the preamble and initial discussion for this article is highly useful and applicable to project management teams as they address the frontend of project planning and execution.  This post summarizes the sage advice provided by Mr. Carson regarding frontend project management challenges as they relate to scheduling and time management. [Read more…]

WAYS OF WORKING – Subject Series Summary

This is McLaughlin and McLaughlins Project Professional’s first Subject Series Summary regarding Ways of WorkingWays of Working aggregates a collection of topics that may be helpful to program and project managers.  This summary update provides an overview of prior posts and provides a baseline for future posts that will follow on a timely basis.

The topics include:

This summary is very brief and simply serves as an index for readers to follow.  Of course, detailed descriptions are contained in the individual posts.  The Subject Series page may also be helpful.  It contains links to several popular series that consist of multiple posts that build upon earlier discussions.

Ideally this Subject Series provides a starting point to investigate best practice on many topics of interest or features of project management.  If you have a suggested topic, please feel free to contact us and let us know. [Read more…]

MANAGING RISK OF DELAY – Subject Series Summary Update

This summary update provides readers with an overview of prior posts and provides a baseline for future posts that will follow on a timely basis.  The last summary was posted on June 12, 2011

This summary is very brief and simply serves as an index for readers to follow.  More robust summaries are provided in the June summary.  Of course, detailed descriptions are contained in the individual posts.

Ideally this summary provides a starting point to investigate best practice on many delay-related features of project management.

The Context and Challenge (Part 1) – Talk/Speech by Mr. Keith Pickavance

Time-Management Strategy (Part 2) – Strategy according to CIOB Guide

As-Planned Schedule / Accepted Programme (Part 3) – Establishing the Time Management Baseline

Schedule Preparation and Maintenance (Part 4) – Managing the Time Baseline

Earned Value Management (Part 5) – Importance and Management of the Time Baseline Tool

Critical Path and Earned Value Management (Part 6) – Managing with Critical Path, Earned Value Management and Productivity Tools

Earned Value and Schedule Performance Indicators (Part 7) – Time Management Tools

Schedule Specification Sources and Implementation (Part 8) – Managerial Tools with sources

Recognition and Notice (Part 9) – Managerial Alerting and Action Tools

Going forward, we will post other features of MANAGING THE RISK OF DELAY. [Read more…]

MANAGING RISK OF DELAY – Forecasting and Management (Part 12)

This post is the twelfth in a series of discussions regarding various aspects of time management as it relates to the risk of delay.  This post addresses the managerial aspects of forecasting related to time management.

Planning for and implementing (time-related as opposed to cost-related) forecasting is, perhaps, one of the most important aspects of Time Management and, consequently, Managing Risk of Delay.  As with progress assessment, timely (early) detection of trends (positive and negative) allows timely managerial action.  Timeliness of action has a heavy influence over the effectiveness of Time Management.  In project work, it is imperative that one finds problems quickly and fixes these problems rapidly.  In order to implement timely action, professional and realistic time forecasting is required.

The challenge associated with managing time is intensified in the case of larger and more complex projects as well as fast-track and high technology projects. [Read more…]

MANAGING RISK OF DELAY – Progress Assessment (Part 11)

This post is the eleventh in a series of discussions regarding various aspects of time management as it relates to the risk of delay.  This post addresses planning for and implementing progress assessment.

Planning for and implementing progress assessment is, perhaps, one of the most important aspects of Time Management and, consequently, Managing Risk of Delay.  Timely (early) detection of trends (positive and negative) allows timely managerial action.  Timeliness of action is a heavy influence over the effectiveness of Time Management.  In project work, it is imperative that one finds problems quickly and fixes these problems rapidly.  In order to implement timely action, professional progress assessment is required.

The challenge associated with managing time is intensified in the case of larger and more complex projects as well as fast-track and high technology projects. [Read more…]

MANAGING RISK OF DELAY – Schedule Updates and Progress Considerations (Part 10)

This post is the tenth in a series of discussions regarding various aspects of time management as it relates to the risk of delay.  This post addresses planning for and implementing progress measurement and schedule updates.

The challenge associated with managing time is intensified in the case of larger and more complex projects as well as fast-track and high technology projects.

In order to professionally manage time (and, therefore, risk of delay) the manager must have a time baseline [typically a Critical Path Method schedule and a Performance Measurement Baseline – please see earlier posts on these topics] and a method to recognize variations from the baseline.  In order to detect variances, the managerial team must have an effective process to measure progress data and update the schedule (or time model). [Read more…]

MANAGING RISK OF DELAY – Subject Series Summary Update

This summary update provides readers with an overview of prior posts and provides a baseline for future posts that will follow on a timely basis.  The last summary was posted on June 12, 2011.

This summary is very brief and simply serves as an index for readers to follow.  More robust summaries are provided in the June summary.  Of course, detailed descriptions are contained in the individual posts.

Ideally this summary provides a starting point to investigate best practice on many delay-related features of project management.

The Context and Challenge (Part 1) – Talk/Speech by Mr. Keith Pickavance

Time-Management Strategy (Part 2) – Strategy according to CIOB Guide

As-Planned Schedule / Accepted Programme (Part 3) – Establishing the Time Management Baseline

Schedule Preparation and Maintenance (Part 4) – Managing the Time Baseline

Earned Value Management (Part 5) – Importance and Management of the Time Baseline Tool

Critical Path and Earned Value Management (Part 6) – Managing with Critical Path, Earned Value Management and Productivity Tools

Earned Value and Schedule Performance Indicators (Part 7) – Time Management Tools

Schedule Specification Sources and Implementation (Part 8) – Managerial Tools with sources

Recognition and Notice (Part 9) – Managerial Alerting and Action Tools

 

Going forward, we will post other features of MANAGING THE RISK OF DELAY. [Read more…]

TIME MANAGEMENT – Schedule Specification Implementation (Part 6)

This Subject Series addresses the sources and implementation of a contract schedule specification.  The Subject Series structure is presented in multiple parts and the series is a logical extension of the series titled MANAGING RISK OF DELAY.  The intention is to capture sources of best practice in Time Management as it relates to implementing a professional schedule specification.

The overview of this series is:

The balance of this post is from the paper.  In general, this informative work compares two approaches to schedule specification implementation.

This extract from the paper covers:

TIME MANAGEMENT – Schedule Specification Implementation (Part 5)

This Subject Series addresses the sources and implementation of a contract schedule specification.  The Subject Series structure is and will be multiple parts and be a logical extension of the series titled MANAGING RISK OF DELAY.

The overview of this series is:

The balance of this post is from the paper.  In general, this informative work compares two approaches to schedule specification implementation.

This extract from the paper covers:

TIME MANAGEMENT – Schedule Specification Implementation (Part 4)

This Subject Series addresses the sources and implementation of a contract schedule specification.  The Subject Series structure is and will be multiple parts and be a logical extension of the series titled MANAGING RISK OF DELAY.

The overview of this series is:

The balance of this post and subsequent ones in this series are/will be from this paper.  In general, this informative work compares two approaches to schedule specification implementation.

This extract  covers: